Bracket correction allowance with no first released dimension

StevenBriggs · 2026年3月26日 11:57 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

ST
StevenBriggs
I can identify the gusseted bracket and its final accepted check in our FR5 planning file. The earlier fixture check says aligned, then fabrication records straightening, but there is no first released dimension. I'm happy to retain the correction history. I'm not happy calling its estimated duration a measured saving for the new fixture.

16 条回复

DI
DineshAdams0125

Could the supervisor identify the basis of that duration separately from the inspection history, so you can retain an estimate without presenting it as a timed result from this bracket?

11分
ST
StevenBriggs

He based it on what he remembers from that product family. It includes waiting for inspection, though he couldn't split the two parts of the allowance.

12分
RO
RobinBaker0512

Then don't label it straightening time. Half the job may be standing around.

9分
RE
ReeceBell0645

Does the recorded correction identify what was changed on this bracket? I mean the actual entry, not the supervisor's recollection of the usual job.

9分
HA
HarishChen1185

Worth checking that. In one file I reviewed, the supposed correction was planned machining already costed elsewhere. The word correction was added in a later summary. Yours may really be straightening, but the original operation description matters

17分
ST
StevenBriggs

Reece, it names straightening of the upright, signed by fabrication. Harish, no planned machining hidden in this one. The missing first released reading still prevents a measured before-and-after comparison.

12分
SI
Simon_Blair

Keep that limit. A signed operation isn't its missing measurement.

7分
OW
OwenAli0225

Who is deciding which current brackets enter the new observation? Selecting only the ones sent for correction would miss the work that already passes.

20分
CA
CalebChan1102

And use one defined inspection method throughout.

17分
ST
StephanieBowen

Include the restrained and released states as different observations. A model holding the bracket at nominal geometry should not be treated as a prediction of its released condition.

15分
ST
StevenBriggs

Quality selected an ordinary current batch, not only failures. We are recording incoming fit-up, fixture identity, first released check, any correction and final check against each bracket. Active work and waiting have separate entries.

19分
NA
NadiaAllen0291

Will that include the correction person's other work, or assume they're always waiting for this bracket?

14分
ST
StevenBriggs

Other work is included. The first observation followed six brackets: four passed at first release, two needed straightening and reinspection. Waiting for the shared inspector took longer than the active correction on those two.

3分
RO
RobinBaker0512

Useful. The queue finally made it onto the sheet.

3分
ST
StevenBriggs

We've removed the old measured-saving claim. The estimator has this six-bracket observation and its scope, plus the supervisor's separately labelled wider estimate. We aren't extrapolating six parts into a guarantee for the FR5 fixture.

18分
DI
DineshAdams0125

Thank you for separating those bases; can the covering planner find the observation and the estimate without having to ask you which number is which?

9分