a cheap arm quote attached to a very mysterious total

JoBarnes0592 · 2025年4月4日 04:56 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

JO
JoBarnes0592
Our UR5e carton-loading estimate now has blanks for fixtures, training and safeguarding, which makes the affordable arm price less comforting; how do I compare two proposals when neither supplier can yet price the whole job?

3 条回复

OM
OmarChen1187

Ask both to list included work, exclusions and unresolved costs against the same task requirements. Unknown costs should remain visible, not turn into zero in your comparison.

14分
JO
JoBarnes0592

We did that and found one supplier had assumed we'd design all the presentation tooling, so the quotes weren't remotely comparable; now we're pricing a defined design stage to answer the biggest unknowns.

4分
OM
OmarChen1187

Make sure that stage says what decisions and deliverables it will produce. Otherwise you may pay for another estimate with different blank spaces.

13分

讨论已关闭

此讨论已连续六个月没有活动,现已关闭新回复。 最后活动: .