Which FR5 tool view should include our mill door handle?

OmarBennett0752 · 2026年1月1日 23:30 UTC

已关闭
OM
OmarBennett0752
The proposed FR5 exchange layout has the aluminium blank at its destination, but the tool body is missing and the open door is just a line. I can get the machine measured. What should the tool supplier put on the same view?

5 条回复

RO
RobinChan1121

The complete held-blank assembly, including fingers, body, adapter and connections, through the required movements. And measure the handle too. A door line has a suspiciously convenient lack of thickness.

11
OM
OmarBennett0752

Machine owner has measured the opening and the door in its intended open position, handle included. Tool supplier still has the rear connection marked to be confirmed.

4
RO
RobinChan1121

Then keep that connection gap visible. Do they show the empty tool leaving after release as well as the blank arriving?

18
OM
OmarBennett0752

They've added the empty route to the request, but no route assessment yet. Rear connection still undefined. Setter's fixture-change access is in the layout too.

9
RO
RobinChan1121

Useful. I'd leave the arm and stand decision open until that actual assembly has been assessed, rather than let the measured door make the unfinished tool look finished.

17