I have left our tooling unfitted because the delivered FR5 interface bracket differs from the configuration accepted against our fixture drawing. The label suffix differs too. After forty days, the seller still offers equivalence without an identified comparison. I need the complete assembly assessed before treating this as a harmless revision.

2 条回复

DA
DavidBrown0954

Has the seller identified the supplied bracket drawing against the delivered package? Give your integrator that and the accepted arrangement, including the connections, so the actual differences can be assessed.

10
TH
TheoAbbott0062

The supplied drawing is now identified. It shows a different connection position, and our integrator has requested the complete loaded assembly information before comparing access and the intended sample transfer. The seller has not supplied that data yet.

16