My FR10 estimate includes no one to release the spacer fixture

IsabelAdams0126 · 2026年2月23日 13:16 UTC

已关闭
IS
IsabelAdams0126
The arm and gripper are priced. Meanwhile our machinist points out that she releases a sticking spacer and cleans the fixture several times during an order. I had treated that as setup. Rather awkward omission. I want a bounded observation before commissioning another fixture concept, but what should we agree to count?

2 条回复

HA
HassanArcher0356

Count the interventions, their reasons and the active work through a representative order and changeover, with waiting separate; fixture release repeated during production belongs in the proposed process, not in an optimistic setup allowance.

14
IS
IsabelAdams0126

We have agreed one observed order and its changeover, with the machinist recording the reason for each release or cleaning interruption. The toolmaker has a paid review slot afterwards. No commitment to build the fixture; that depends on what the observation shows.

17