The arm and gripper are priced. Meanwhile our machinist points out that she releases a sticking spacer and cleans the fixture several times during an order. I had treated that as setup. Rather awkward omission. I want a bounded observation before commissioning another fixture concept, but what should we agree to count?
Count the interventions, their reasons and the active work through a representative order and changeover, with waiting separate; fixture release repeated during production belongs in the proposed process, not in an optimistic setup allowance.