简体中文界面。帖子、指南及政策正文保留原文;未对原文作自动翻译。

The FR10 moves the bags but I keep rebuilding the presentation

MiaBaker0470 · 2026年7月25日 19:16 UTC

回复讨论
MI
MiaBaker0470
I've put a lot into our FR10 bag-to-carton setup, starting with 92 filled sample bags. The motion is working, but another bag shape means another round of presentation work, and the products keep changing. I'm attached to what I've built and struggling to decide how much ongoing attention this process deserves.

8 条回复

TH
ThomasBrooks0799

Separate the working transfer from the work required to feed it. Your effort is real. It does not tell you whether the next bag change is worth accepting.

22
LU
LucaChan1048

Could somebody else handle the next change from your notes?

17
MI
MiaBaker0470

Not comfortably, Luca. The notes cover the current bag, but most of the presentation decisions are still mine. I don't want to call that operator reluctance when I haven't given them a repeatable changeover.

24
TH
ThomasBrooks0799

Then the comparison needs a support allowance. Include your preparation time and someone else's learning time, but keep them separate. A one-off handover cost is different from adjustment every time the product changes.

8
LU
LucaChan1048

Thomas, would restricting it to the established bag avoid scrapping useful work?

9
TH
ThomasBrooks0799

Possibly. It would need enough work of that shape to justify keeping the setup available. Restricting its scope is a sensible option to cost, not evidence that keeping it will pay.

6
MI
MiaBaker0470

I've stopped adding new bag shapes for now, and we're recording the preparation alongside the transfer. That feels less like a verdict on all the effort, which helps. The established shape stays under review while we work out who could actually support it.

3
LU
LucaChan1048

Thanks for coming back. Interested whether that narrower job survives the support review.