UR5e lathe plan with two meanings of ready

FelixAllen0284 · 2025年10月5日 23:10 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

FE
FelixAllen0284
Our interface meeting ended with both suppliers agreeing ready. One meant request received, the other meant loading space available. I'm writing the spacer-blank sequence and need two definitions, not one agreeable word.

1 条回复

NO
NoraBrooks0844

Put request receipt and loading availability in separate rows with their owners, set and clear conditions, then walk both teams through normal, timeout and restart sequences; keep these ordinary process states distinct from the engineered safety permissions.