UR5e lathe plan with two meanings of ready

FelixAllen0284 · 5 Oct 2025, 23:10 UTC

Closed
FE
FelixAllen0284
Our interface meeting ended with both suppliers agreeing ready. One meant request received, the other meant loading space available. I'm writing the spacer-blank sequence and need two definitions, not one agreeable word.

1 reply

NO
NoraBrooks0844
Replying to FelixAllen0284

Put request receipt and loading availability in separate rows with their owners, set and clear conditions, then walk both teams through normal, timeout and restart sequences; keep these ordinary process states distinct from the engineered safety permissions.