Our brass-blank transfer proposal shows the FR5 reaching inside the machine, but the tool body is absent and the open door is outside the drawing. I don't see how we can accept a base position yet. What should I ask the integrator to bring to the layout review?

6 条回复

DA
DanielAdams0130

Can they show the actual loaded tool assembly through the full approach and withdrawal, together with the measured door in its operating positions?

-2分
EM
EmmaArcher0376

They can add the gripper, but the adapter is still an outline and the door survey isn't done. I've asked for both. The current reach picture seems too incomplete to price installation from.

6分
DA
DanielAdams0130

Who is providing the missing adapter dimensions, and is that included in the integrator's proposed design work?

13分
EM
EmmaArcher0376

Integrator owns the adapter design. Door survey is with our maintenance team. Both are in the review request now. Thanks for the ownership question; everyone had previously just said someone would supply the details.

19分
DA
DanielAdams0130

Will the reviewed layout also show where the setter stands and changes the fixture?

6分
CA
CallumBrooks0795

That belongs in the review, but you can still compare clearly provisional candidates while the survey is being completed. I mean compare options and missing information, not approve the base or assume the existing drawing has proved access.