The FR10 fits once the drawing removes our door

HollyBailey · 2025年9月6日 22:33 UTC

已关闭
HO
HollyBailey
Our brass-blank unloading proposal puts the FR10 in a convenient corner, but the reach sketch leaves out the open machine door and the whole gripper body. The drawing is being passed around as a fit check. I want it labelled honestly while we ask for the missing geometry.

16 条回复

JA
JasperArcher0377

Call it a provisional reach sketch and ask the integrator for the loaded tool, adapter and fittings through the complete withdrawal. Add measured door positions. Or rather, have the actual opening surveyed first if that rectangle is only an estimate.

22
HO
HollyBailey

Maintenance has measured the door. Adapter is not defined yet, though the gripper supplier has supplied its body and finger drawings. I've put provisional on the sketch and asked who is designing the remaining piece.

17
EL
ElliotChan1118

Check the finger-open shape too. The closed tool may leave the blank in the right place and then hit something when it releases.

14
HO
HollyBailey

Integrator owns the adapter now. Open fingers are included. They found the loaded withdrawal crosses the door handle and proposed a shorter adapter or a different base position.

8
JA
JasperArcher0377

Both need proper review. The shorter adapter changes the loaded assembly as well as clearance, so include the applicable load assessment for the proposed motion. A base move has installation and access consequences of its own.

17
NO
NoahBarnes0542

Could a full-size tool envelope reject either candidate cheaply while the modelling catches up? It won't establish the whole application, but it might stop you paying for detail on an obviously blocked doorway.

-3
JA
JasperArcher0377

Yes, as an early clearance check. Keep it identified with the candidate geometry, though. A smaller convenient outline can give you a very encouraging answer to a question nobody intended to ask.

5
BR
BrunoAli0191

Where does the proposed new base go? Maintenance access is easy to forget when the immediate argument is all about a door handle.

16
HO
HollyBailey

Bruno, farther towards the end of the machine, beside the service panel. Noah, toolroom has the proposed envelopes for a first check. The setter is also checking fixture-change access at that position.

1
EL
ElliotChan1118

Include the trolley turning space if the setter uses one. I have seen a route drawn as a line that could only be followed by a trolley with no width.

16
BR
BrunoAli0191

Panel removal too, not only opening its door. Sometimes the service job needs the piece lifted out and carried away.

21
HO
HollyBailey

The farther position obstructs panel removal, so maintenance ruled it out. Setter's trolley access was also poor. Shorter adapter remains a proposal; the first outline clears the handle, but the complete motion review is unfinished.

14
JA
JasperArcher0377

Does that remaining review include the loaded exit and empty return? Clearing the handle in one outline is useful, but I would keep the installation choice open until both routes are covered.

12
NO
NoahBarnes0542

And is the shorter adapter still a price the supplier stands behind, or did it become a new design charge? Worth keeping the cost next to the geometry decision.

14
HO
HollyBailey

Jasper, both routes are in the review. Noah, a revised design price is requested. No base or adapter accepted yet. The floor plan has the rejected location removed and the original one marked provisional.

6
BR
BrunoAli0191

Make sure that panel-removal space stays on the drawing after the decision. It is still needed even when the robot moves somewhere else.

18

讨论已关闭