My FR10 saving still needs my colleague at the fixture

AnilArcher0375 · 2026年1月28日 08:16 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

AN
AnilArcher0375
I priced an FR10 to unload connector housings. My colleague asked who releases the fixture, checks the housing and changes the receiving tray. Apparently my labour saving has three unpaid helpers. What should a small pilot settle first?

14 条回复

HA
HarishBrooks0837

Follow one ordinary order through the current job before borrowing a robot. Include those three tasks and the interruptions. You're trying to find a chunk of work that can actually move away from your colleague, not make the arm look busy.

19分
AN
AnilArcher0375

We already have a shift sheet, but it only counts finished housings. Doesn't show who clears the fixture. I'll ask for an observation with that included.

15分
LU
LuisBrooks0869

I once timed unloading as the seconds between picking up a part and putting it down. The operator politely let me finish, then showed me the fixture cleaning, the awkward part she put aside and the tray she had to fetch from another room. My little timing wasn't false; it just wasn't the job. Keep a whole order visible, including the last few housings. If a proposed pilot needs somebody standing there doing the omitted work, give that person a name in the staffing plan and count their time. They do not become free because the robot is in the photograph.

14分
AN
AnilArcher0375

Colleague agreed to the observation, provided it doesn't become an unofficial extra shift. Fair condition. Supervisor has to arrange cover before we do it.

13分
HE
HenryBaker0438

Can the fixture release itself in the proposed job, or have you only priced the gripper?

6分
HA
HarishBrooks0837

Luis, yes to the full order, but I'd still break out the tasks inside it; Anil needs to know whether one expensive exception is hiding an otherwise useful option.

20分
LU
LuisBrooks0869

Agreed, I mean observe the whole order, not squash it into one average.

7分
DA
DanielBrown0913

Include where suspect housings go. A tidy output tray can conceal a little reject pile that someone else spends the afternoon sorting. Quality needs to own that decision in the pilot.

6分
AN
AnilArcher0375

Henry, only the gripper. Fixture release wasn't in my quote. Daniel, quality currently takes the suspect ones at the bench, so that handoff belongs in the observation too.

9分
HE
HenryBaker0438

Then ask for the complete fixture option before anyone treats your price as a purchase budget.

10分
AN
AnilArcher0375

Supervisor arranged cover and we observed an order. Unloading was brief; release and cleaning kept bringing my colleague back. I've withdrawn the staffing saving and asked for a fixture-inclusive concept, not a robot trial date.

13分
DA
DanielBrown0913

Did the suspect-part handoff take much of that person's time, or was fixture work the main interruption?

11分
AN
AnilArcher0375

Fixture work was the repeated interruption. Two suspect housings went to quality together. Thanks Luis, the whole-order view caught the cleaning that my original timing never saw.

11分
HA
HarishBrooks0837

That's enough to stop using the old saving. Whether a redesigned fixture earns its cost is another question, and your colleague shouldn't have to fund the answer with spare time.

4分