Who signs off the unload path with the finished part attached?

EmmaBarnes0550 · 2024年12月23日 10:06 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

EM
EmmaBarnes0550
I reviewed a proposed FR5 unload layout with our setter. Empty gripper fits through the opening; nobody has drawn it holding the brass blank. Who normally supplies that complete path review before we accept a quotation?

1 条回复

MA
MayaChen1171

What does the quotation actually assign to the integrator? If tooling and access validation are absent, get them included with a named deliverable. Otherwise everyone can assume someone else checked it.

11分