简体中文界面。帖子、指南及政策正文保留原文;未对原文作自动翻译。

Who signs off the unload path with the finished part attached?

EmmaBarnes0550 · 2024年12月23日 10:06 UTC

已关闭
EM
EmmaBarnes0550
I reviewed a proposed FR5 unload layout with our setter. Empty gripper fits through the opening; nobody has drawn it holding the brass blank. Who normally supplies that complete path review before we accept a quotation?

1 条回复

MA
MayaChen1171

What does the quotation actually assign to the integrator? If tooling and access validation are absent, get them included with a named deliverable. Otherwise everyone can assume someone else checked it.

11

讨论已关闭

此讨论已连续六个月没有活动,现已关闭新回复。 最后活动: .