Was that single sheet supported on a bench during the seal test?
简体中文界面。帖子、指南及政策正文保留原文;未对原文作自动翻译。
one panel sealed, stack transfer still untested
AmaraBell0687 · 2025年7月18日 17:41 UTC
19 条回复
Yes, flat on the bench. No lifted-panel view in the report.
19分Then you haven't seen how the free edges behave. Ask for the actual supported span.
8分Asked. The overhanging corners worry me more than the middle.
13分Watch the corners entering the nest too. A panel can hang clear and still catch the lip on placement.
22分Are the panels stacked in the same surface condition used for the trial? Protective film, residue or moisture between sheets could change how they separate, so I would send a representative stack rather than loose selected panels.
2分Production stack has interleaves. Test panel was supplied loose. Thanks, Ada, that's a missing bit.
7分Our teaching example lifted a second thin sheet that nobody noticed until the placement went wrong. The vacuum indication looked entirely pleased with itself. I would ask the supplier how they detect or otherwise verify a single panel, and what the station does when that check is uncertain. It is much easier to discuss that before a double has reached the nest.
12分How are the interleaves removed, Amara?
18分And make the support arrangement part of the supplied tool definition, not a helper holding a corner for the video; maintenance needs to know which bits keep the panel shape under control.
9分I'd compare a manually prepared stack as well. Might be cheaper than automating interleaf handling for small runs.
20分Operator removes each interleaf in the proposal. I hadn't included that time. We need both options costed.
13分Removing interleaves by hand doesn't answer whether two metal panels can travel together.
20分I didn't say it did. I'm questioning the extra interleaf equipment, not the single-panel check.
5分Amara, does the proposed operator task occur at a separate preparation position, or beside the robot's pick location? That affects the workflow and the access arrangements the integrator needs to review.
2分Maya's cost comparison is sensible. I'd still insist both proposals use the same real stack conditions and the same acceptance checks, otherwise the cheaper one may simply leave more work to the operator.
22分Separate preparation position. Integrator is reviewing the operator exchange. Supplier agreed to test corner support, separation and nest entry with our actual stack materials.
14分First trial found a corner catching the nest lip. Single-panel verification worked in the tested cases. Tool support is being revised; no complete transfer acceptance yet.
11分Will the revised support still leave access to replace the cups? Worth asking while the drawing is open, before a useful stiffener turns a routine change into dismantling half the tool.
8分讨论已关闭