简体中文界面。帖子、指南及政策正文保留原文;未对原文作自动翻译。

Why rank the FR10 when the demos unload into different trays?

YasminChan1050 · 2026年2月21日 21:26 UTC

已关闭
YA
YasminChan1050
Both sleeve demos moved parts. Only one used our receiving tray. What comparison would settle the extra handling?

17 条回复

OS
OscarBennett0706

What happens to the sleeves after the demonstration tray is full? Ask for that before comparing the robot cycle times.

6
YA
YasminChan1050

Our tray goes to assembly. Their demonstration tray would need unloading into ours first.

13
CA
CallumAllen0273

Did either demonstration show release into the awkward pockets, or did the video stop while the sleeve was still held?

13
AI
AishaBarnes0605

Price the transfer between trays as a distinct option. It may still be workable, but the person doing it and the space for both trays belong in that price.

8
YA
YasminChan1050

Callum, our-tray demo showed release. Two sleeves needed the demonstrator to straighten them afterwards.

25
LE
LeahAdams0147

Then ask what the ordinary loader would do with those two. I'd want the supplier to explain the placement problem before a tutor quietly inherits a manual finishing step.

19
AN
AnilAbbott0027

Leah, manual finishing might be an honest option if it is acceptable and costed. The trouble is presenting it as an autonomous transfer and then telling the loader it is only an occasional touch.

11
CH
ChenChan1051

Two out of how many? Occasional needs a denominator.

5
OW
OwenAli0225

Were those two pockets damaged, or were they ordinary examples of the tray you intend to use? I would not ask a new tool to accommodate scrap without first knowing the distinction.

14
YA
YasminChan1050

Two out of twelve sleeves. Tray inspected and acceptable for assembly use; those pockets are not damaged.

2
LU
LucyChan1089

Anil's option deserves a price, not a euphemism. Include the loader examining the tray, identifying a poor placement, and putting it right through an agreed method. Counting only the seconds spent straightening two sleeves will flatter it.

9
LE
LeonBriggs

And show how the loader knows a sleeve is properly seated afterwards

22
VA
Val_Bailey

Does assembly accept a different tray at all? Could remove the second transfer, if they do.

16
CA
CarlaArcher0401
回复 Val_Bailey

Worth asking, Val, but also who returns the empty trays. We once priced new trays and forgot the collection job entirely.

9
YA
YasminChan1050
回复 Val_Bailey

Assembly will consider another tray, provided its fixture interface stays unchanged. Supplier is pricing a compatible receiving tray.

4
LE
LeahAdams0147

That changes the choice usefully. Anil, I accept your point about a costed manual option; I'd keep it beside this new tray proposal until the actual placement and handover are demonstrated.

25
OS
OscarBennett0706

Has the proposed receiving tray been assessed at assembly yet, including the fixture interface and empty return? I would hold the shortlist until that answer joins the handling cost.

8

讨论已关闭

此讨论已连续六个月没有活动,现已关闭新回复。 最后活动: .