Our FR5 fixture review has aligned-under-restraint notes and failed released dimensions, but no paired numerical restrained readings; how should I retain the useful history without making the unexplained correction our new process?
A separate correction. The route lists it between released inspection and final acceptance, but gives no bracket-level before-and-after readings or method for that operation
Then keep that whole route visible in the estimate, with correction and reinspection as distinct work, and have quality define a new traceable study if the old records cannot explain the released result
Not from these sheets. I've separated the documented sequence from missing measurement conditions, with incoming fit-up, locating scheme and released acceptance listed as questions for the new study
Keep those as questions until their owners answer them, Lin; a new worksheet is useful, but filling its blank stages from assumptions would recreate the same unexplained success story in cleaner handwriting