Fairino FR5: My colleague has a point about the missing labour

KaiArcher0367 · 2026年7月13日 15:11 UTC

回复讨论
KA
KaiArcher0367
I'm pushing for Fairino FR5 to do fixture unloading with a small plastic enclosure in a shared production room, starting with 217. I priced the arm and gripper. Fixtures and staff time? Much vaguer. My colleague's annoyed, fairly enough. I'd like a small pilot we can both judge.

6 条回复

EL
ElenaAli0253

Do your observations cover the manual workflow from preparation to completion? A transfer-only baseline could omit the same activities that made the initial budget incomplete.

23
KA
KaiArcher0367

We watched a batch. Preparation took longer than transfer. My estimate had basically made that work disappear by wishing.

6
EL
ElenaAli0253

Build a capped pilot around the complete workflow. Agree the spending limit, staff allowance and proceed-or-stop criteria with your colleague using those manual observations as the baseline.

14
KA
KaiArcher0367

Count my fixture time too? I'd enjoy it, but it's extra work.

15
AA
AaronArcher0349

On our separate project, we included that time. The design was enjoyable, but our normal workload still needed doing. The estimate became less cheerful.

16
EL
ElenaAli0253

Multiply the manual minutes eliminated by the labour rate for a simple saving figure, then compare that with what the pilot costs.

24