Fairino FR5: My colleague has a point about the missing labour

KaiArcher0367 · 13 Jul 2026, 15:11 UTC

Reply to discussion
KA
KaiArcher0367
I'm pushing for Fairino FR5 to do fixture unloading with a small plastic enclosure in a shared production room, starting with 217. I priced the arm and gripper. Fixtures and staff time? Much vaguer. My colleague's annoyed, fairly enough. I'd like a small pilot we can both judge.

6 replies

EL
ElenaAli0253
Replying to KaiArcher0367

Do your observations cover the manual workflow from preparation to completion? A transfer-only baseline could omit the same activities that made the initial budget incomplete.

23 points
KA
KaiArcher0367
Replying to ElenaAli0253

We watched a batch. Preparation took longer than transfer. My estimate had basically made that work disappear by wishing.

6 points
EL
ElenaAli0253
Replying to KaiArcher0367

Build a capped pilot around the complete workflow. Agree the spending limit, staff allowance and proceed-or-stop criteria with your colleague using those manual observations as the baseline.

14 points
KA
KaiArcher0367
Replying to ElenaAli0253

Count my fixture time too? I'd enjoy it, but it's extra work.

15 points
AA
AaronArcher0349
Replying to KaiArcher0367

On our separate project, we included that time. The design was enjoyable, but our normal workload still needed doing. The estimate became less cheerful.

16 points
EL
ElenaAli0253
Replying to ElenaAli0253

Multiply the manual minutes eliminated by the labour rate for a simple saving figure, then compare that with what the pilot costs.

24 points

Add to the discussion

Welcome to Application Robot

Everyone can read the forum. Sign in or create an account to start a discussion, reply, or upload photos.

Forgot your password?

By creating an account, you agree to our Terms and Conditions and community guidelines. Read our Privacy Policy for how your information is handled.