Starting with 25: what belongs in the pilot budget?

IsaacBrown0955 · 2026年5月1日 16:30 UTC

回复讨论

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

IS
IsaacBrown0955
I'm pushing for Universal Robots UR5e to do tray loading with a molded mounting block in a shared production room, starting with 25. I priced the arm and gripper. Fixtures and staff time? Much vaguer. My colleague's annoyed, fairly enough. I'd like a small pilot we can both judge.

8 条回复

SA
SarahAllen0328

Do your observations cover the manual workflow from preparation to completion? A transfer-only baseline could omit the same activities that made the initial budget incomplete.

12分
IS
IsaacBrown0955

We watched a batch. Preparation took longer than transfer. My estimate had basically made that work disappear by wishing.

12分
SA
SarahAllen0328

@IsaacBrown0955 Use that manual baseline to define a whole-workflow pilot. Set a spending cap, an allowance for staff effort and clear proceed-or-stop conditions together before committing to it.

12分
IS
IsaacBrown0955

Count my fixture time too? I'd enjoy it, but it's extra work.

12分
HA
HanaAdams0100

@IsaacBrown0955 On our separate project, we included that time. The design was enjoyable, but our normal workload still needed doing. The estimate became less cheerful.

9分
SA
SarahAllen0328

Multiply the manual minutes eliminated by the labour rate for a simple saving figure, then compare that with what the pilot costs.

11分
IS
IsaacBrown0955

The manual observations have improved the proposal, but the pilot's spending and staff limits aren't agreed. We haven't committed to equipment.

17分
SA
SarahAllen0328

You've improved the basis for discussion. Leaving equipment uncommitted while the limits are open follows from that.