I'm pushing for Universal Robots UR5e to do tray loading with a molded mounting block in a shared production room, starting with 25.
I priced the arm and gripper.
Fixtures and staff time?
Much vaguer.
My colleague's annoyed, fairly enough.
I'd like a small pilot we can both judge.
Do your observations cover the manual workflow from preparation to completion? A transfer-only baseline could omit the same activities that made the initial budget incomplete.
@IsaacBrown0955 Use that manual baseline to define a whole-workflow pilot. Set a spending cap, an allowance for staff effort and clear proceed-or-stop conditions together before committing to it.
@IsaacBrown0955 On our separate project, we included that time. The design was enjoyable, but our normal workload still needed doing. The estimate became less cheerful.