fr5 inspection handover is mostly screenshots

PavelArcher0353 · 2025年10月24日 22:40 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

PA
PavelArcher0353
I need the installed revision and called routines for our bracket inspection. Screenshots cover neither. Integrator still available.

13 条回复

CA
CarlaAbbott0053

On an inherited fixture we found the screenshots described a different nest. Ask for the complete installed program export with its revision and the fixture assumptions, not simply more pictures of the main routine.

13分
ME
MeiAdams0168

And the ordinary PLC exchange needs its own description. We have just withheld a lesson until both sides demonstrated the agreed normal and interrupted behaviour. Buttons and screenshots were not enough.

21分
PA
PavelArcher0353

Requested both. The main routine calls inspect_bracket, which is absent from the supplied folder.

4分
HA
HarishCarter1011

Name that missing dependency in the request, so the integrator knows another copy of the main routine will not close it.

7分
EL
EllaAllen0294

Does the fixture shown in the screenshots match what is fitted? It may help to photograph the installed identifier now, while the integrator can explain any difference.

11分
PA
PavelArcher0353

Fixture label matches drawing D. Screenshots have no readable identifier, so I can't assign them confidently.

17分
CA
CarlaAbbott0053

Keep them as unverified illustrations until the integrator matches them. The current label and drawing give you a starting point, but the handover should describe the actual installed arrangement and its required checks.

4分
ME
MeiAdams0168

Can the maintainer open the eventual export with their normal account? We had a wonderfully complete folder that only the visiting person's setup could use.

18分
HA
HarishCarter1011

Mei, that check belongs in the handover session too, not just in an email saying the backup was delivered.

13分
PA
PavelArcher0353

Called routine arrived. Integrator matched revision 4 to the installed job. Maintainer-account check still pending. Ordinary signal table incomplete.

8分
EL
EllaAllen0294

Which part of the signal table is missing, Pavel? That may help you get a targeted answer before the integrator finishes their involvement.

16分
PA
PavelArcher0353

Who clears the inspection request and what acceptance means. Asked both program owners to agree those entries.

12分
ME
MeiAdams0168

Keep those meanings distinct from completion, and have the handover demonstrate an interruption as well as the neat exchange. We removed keep-pressing advice from our own lesson for a reason.