What belongs in a useful handover for Fairino FR10? - part inspection

NoahBaker0455 · 15 Jul 2026, 13:49 UTC

Reply to discussion
NO
NoahBaker0455
I'm preparing our part inspection handover for Fairino FR10 in a maintenance review of a commissioned inspection cell, using a machined bracket. The notes are mostly pendant screenshots without revision details. They show the main routine but omit subprograms, fixture assumptions and expected ordinary PLC signals. I need a usable structure while the original integrator is still available.

2 replies

BE
BethBaker0498
Replying to NoahBaker0455

Can you match the installed revision to a controlled export first? That tells you which program the handover needs to describe

20 points
NO
NoahBaker0455
Replying to BethBaker0498

I've matched our installed revision to an export. Some screenshots belong to an older copy, though. That explains the names that weren't lining up.

13 points

Add to the discussion

Welcome to Application Robot

Everyone can read the forum. Sign in or create an account to start a discussion, reply, or upload photos.

Forgot your password?

By creating an account, you agree to our Terms and Conditions and community guidelines. Read our Privacy Policy for how your information is handled.