Our UR5e bracket quote includes an in-fixture angle check but omits the released inspection and correction on the old route; how do I get those jobs assessed before planning gives away their bench space?
Give the supplier the old route and ask fabrication and quality to define the required released check for the current bracket. Keep the omitted work and space provisional until a trial supports removing them. A good reading under restraint doesn't answer that question.