the ur5e study still needs somebody to make its fixtures

JackAli0254 · 18 Dec 2025, 15:59 UTC

Closed
JA
JackAli0254
I priced a spacer-unloading pilot without pricing my colleague's fixture work. What bounded study would let us compare the complete task before either of us commits to building it?

3 replies

TH
TheoBrooks0845
Replying to JackAli0254

Define its questions, deliverables, staff allowance and stop point before pricing any physical pilot.

6 points
JA
JackAli0254
Replying to TheoBrooks0845

We have agreed to compare preparation through the finished tray, including interruptions. The designer is pricing options and a review, not production tooling. My colleague's time allowance still needs agreement.

5 points
TH
TheoBrooks0845
Replying to JackAli0254

Keep that allowance unresolved in the total. Agreeing the task doesn't make his time free.

21 points