Our FR10 aluminium-blank proposal still reaches the fixture with a point, while the full gripper and open door are missing. I want the rear connection and its maintenance access included from the start, alongside loaded withdrawal and empty return. Which combined views would make those requirements clear to the integrator?
Ask for the complete assembly in its relevant loaded and open states through the measured machine opening, plus the actual access needed to disconnect and remove it. Have the setter and maintenance mark their required space on that same layout; a successful route can still leave the connection unreachable.