Which UR5e bracket costs belong after the released failure?

LiamChen1186 · 28 Dec 2025, 14:13 UTC

Closed
LI
LiamChen1186
Our UR5e estimate shows final acceptance but leaves the bracket's correction blank. What should I ask the estimator to separate?

8 replies

LI
LinArcher0357
Replying to LiamChen1186

Ask what happened between the released failure and the final acceptance, using one identifiable bracket if the records allow it. I would separate the correction operation, inspection work and waiting rather than put the whole elapsed gap into a box called rework. You may discover that nobody timed the hands-on work. That is still a useful answer for purchasing: the allowance is unresolved and needs observation. A neat number copied from the final inspection timestamp would be easier to compare and much harder to defend.

6 points
LI
LiamChen1186
Replying to LinArcher0357

Same bracket is identifiable. Two shifts between checks, no recorded correction duration.

18 points
DI
DineshBrown0908
Replying to LiamChen1186

Ask the technician what work the entry describes. Use that to define the current study, not to turn two shifts into hands-on correction time.

23 points
LI
LiamChen1186
Replying to DineshBrown0908

Technician describes correction at a separate bench. Most of the gap was waiting for availability.

6 points
LI
LinArcher0357
Replying to LiamChen1186

Then the waiting belongs in the delivery picture even if it is not active correction cost. Does the proposed process depend on that same person and bench, or has the estimate assumed they will somehow be available whenever the robot finishes?

16 points
LI
LiamChen1186
Replying to LinArcher0357

Same person, already assigned other work. No agreed availability for this cell.

11 points
DI
DineshBennett0734
Replying to LiamChen1186

Put that dependency into the estimate now, with active work and waiting both unresolved where unmeasured; the production plan cannot borrow the same person's time twice just because one operation sits outside the robot drawing

5 points
LI
LinArcher0357
Replying to DineshBennett0734

Who will own the next decision when the study returns? I'd want purchasing, fabrication and inspection looking at the same route, rather than each pricing only the operation they recognise.

7 points

Discussion closed