Which bracket work does our FR5 estimate mean by dressing?

ClaraBaker0437 · 17 Dec 2025, 02:22 UTC

Closed
CL
ClaraBaker0437
I thought I'd finally found the missing correction time in our bracket history, then the fabricator said dressing meant cleaning up incoming pieces on his sheet and straightening a released assembly on the estimator's. Same word, quite different afternoon. Our FR5 proposal has one allowance called dressing. Before I put money against it, can we split the incoming preparation from the released check and any correction, and find out which parts actually need each job?

18 replies

AN
AnilArcher0375
Replying to ClaraBaker0437

Yes. Ask each person what physical work their entry describes and where it occurs in the route. The shared word is not a usable operation definition.

19 points
CL
ClaraBaker0437
Replying to AnilArcher0375

The fabricator removes incoming edge burrs before fit-up; the estimator meant correction after the released dimensional check. Neither was trying to count both, which is how we lost one job entirely.

13 points
BR
BrunoChan1061
Replying to ClaraBaker0437

Then keep two lines, with the decision that sends a part to each; not every incoming piece or released bracket will necessarily need the same treatment.

19 points
TH
ThomasBrooks0799
Replying to ClaraBaker0437

Does the current evidence identify those pieces individually? If one batch total covers both activities, splitting the label will not tell you how much of either was done.

20 points
CL
ClaraBaker0437
Replying to ThomasBrooks0799

Batch totals only, Thomas. The fabricator can explain his normal method but cannot give me a reliable split of that old total. I don't want to divide it in half just to fill the two boxes.

17 points
SA
SarahBrown0937
Replying to ClaraBaker0437

I have seen a remembered busy shift become the standard allowance, so I would use his explanation to plan the observations rather than turn it into times for the old batch.

17 points
AN
AnilArcher0375
Replying to ClaraBaker0437

Also distinguish waiting from the work itself. Or rather, record both; the waiting still affects the route even if it does not belong in hands-on correction time.

16 points
BR
BrunoChan1061
Replying to AnilArcher0375

Anil, yes, especially if the same person does both jobs and is meant to supervise something else in the new layout.

21 points
CL
ClaraBaker0437
Replying to BrunoChan1061

It is the same fabrication technician. Our proposed staffing has him feeding another station too. That's now an open issue beside the two work lines, not hidden inside one guessed allowance.

11 points
TH
ThomasBrooks0799
Replying to ClaraBaker0437

For the dimensional comparison, keep incoming fit-up, fixture contacts and the released measurement method with the identified assemblies. Otherwise a different starting condition may be mistaken for an effect of the proposed fixture.

13 points
SA
SarahBrown0937
Replying to ClaraBaker0437

Will the technician and inspector both help define the sample route, Clara? They may disagree about where preparation ends and a rejected component needs a separate decision.

16 points
CL
ClaraBaker0437
Replying to SarahBrown0937

Both are involved. The inspector has already asked us not to describe every incoming defect as something the technician can simply dress away. We need the acceptance and rejection decisions written down too.

7 points
BR
BrunoChan1061
Replying to ClaraBaker0437

Good catch. Preparation isn't permission to rescue every component.

10 points
AN
AnilArcher0375
Replying to ClaraBaker0437

What decision will the first study support: understanding the present work, or choosing the new fixture? Those need not be the same study.

14 points
CL
ClaraBaker0437
Replying to AnilArcher0375

Understanding the present work first, Anil. The proposed fixture changes the locating scheme, so it will need its own comparison afterwards. Thanks for making me say that plainly; the estimate was skipping straight to the second decision.

16 points
TH
ThomasBrooks0799
Replying to ClaraBaker0437

That is a useful scope. Keep the existing fixture revision and sample-selection method in the result, so the later comparison does not inherit another unexplained average.

20 points
CL
ClaraBaker0437
Replying to ThomasBrooks0799

The current-route study has started with individually identified assemblies and separate entries for preparation, released check, correction and final check. No result yet. The FR5 buying decision is still open.

1 points
SA
SarahBrown0937
Replying to ClaraBaker0437

Did the study show whether that shared technician could cover the proposed work, Clara, or is the sample still too limited to answer?

17 points