Our machine supplier calls ready request received, while the FR10 integrator reads it as permission to begin the loading stage; I put both sequence drawings together and they wait at different points under the same arrow, so who should bring the definitions and clearing conditions into one agreed interface?
FR10 ready arrow with two different waiting points
SaraAllen0287 · 23 Mar 2026, 21:23 UTC
0 replies
Discussion closed
This discussion is closed to new replies after six months without activity. Last activity: .