Which tool geometry should I give the FR10 access reviewer?

LuisAli0260 · 23 Jul 2025, 02:06 UTC

Closed
LU
LuisAli0260
Our steel-blank loading sketch reaches the fixture but leaves out the gripper and open door, so I cannot use it to explain the proposed cell to operators; what should I ask the supplier to include before anyone selects a base position?

2 replies

VI
VictorAli0185
Replying to LuisAli0260

The complete proposed tool holding the blank, with adapter and service fittings, through entry and withdrawal. Include the actual machine opening and open-door fittings. Have the setter review fixture changeover access from that same layout.

24 points
LU
LuisAli0260
Replying to VictorAli0185

They had an old door outline and a tool centre point, nothing more; the machine owner and toolmaker are supplying the current geometry, and the mounting decision is waiting for that combined review

19 points