Agree the decision the pilot must answer before deciding its equipment. Start with the present unloading job, including preparation, changeovers and awkward handling, then choose the smallest assessed trial that measures the uncertainty both of you think matters.
What would make our enclosure-unloading pilot a fair budget test?
CalebAdams0145 · 20 Aug 2026, 19:45 UTC
21 replies
Who prepares the enclosures and clears the finished ones while your robot is apparently saving labour?
20 pointsOur cheap pilot became a permanent fixture development job. Put a spending limit and a stop decision in writing before the first special part is ordered.
20 pointsI had assumed the existing operator would prepare and clear between other jobs. That time was not priced. We need to compare complete orders, not the unload movement alone.
22 pointsWhich current order best represents the changeovers that make your colleague doubt the proposal? A long uninterrupted run may be useful later, but it may not answer this disagreement.
23 pointsThomas's spending limit helps, though I would include a useful next decision as well as stop. A pilot can find a narrower worthwhile job even when the original all-products claim does not survive.
15 pointsWe selected a recent mixed order with two enclosure variants. My colleague wants the fixture change included and the same finished output counted for manual and assisted routes.
7 pointsWhat happens when the second variant turns up before the first one is finished?
13 pointsThat's the bit our quote called a simple changeover. Simple for the person who made the fixture, less simple for everyone else.
17 pointsInclude that interruption as a defined case if it occurs in the actual work. Do not add every imaginable disruption, or the small pilot will never have a boundary.
7 pointsIt occurs often enough to include. We have a capped proposal for an assessed supplier trial and a separate current-method observation; no arm order. Fixture preparation is itemised instead of absorbed into demonstration time.
16 pointsKeep discomfort and awkward handling observations alongside the time figures. You might accept a little more preparation to remove a genuinely difficult task, but that benefit should come from the comparison rather than from general enthusiasm for automation.
8 pointsWho pays to revise the fixture if the first trial cannot handle the second variant?
16 pointsNo automatic revision budget. The first trial is complete under the agreed setup: the second variant needed manual presentation and a fixture reset, so the mixed order used more staff time than the current route.
24 pointsDid that include your own assistance, or only the operator's time?
16 pointsBoth, including my fixture help and the change back. The operator did not identify a handling improvement sufficient to justify that extra work in this comparison.
9 pointsThen the original mixed-order proposal has not earned the purchase. A stable-variant application could be a separate question, but it should not be used to reinterpret a comparison that included the actual interruptions for a reason.
12 pointsHave you and your colleague made the purchase decision from those results?
13 pointsWe have decided against buying for this unloading job. We will retain the current method and the trial records, rather than fund another fixture revision to avoid admitting the comparison went against my idea.
21 pointsThat is what the stop decision was for; useful work can end with no purchase.
15 pointsAdd to the discussion
Welcome to Application Robot
Everyone can read the forum. Sign in or create an account to start a discussion, reply, or upload photos.
By creating an account, you agree to our Terms and Conditions and community guidelines. Read our Privacy Policy for how your information is handled.