bracket records with different measurement conditions

ClaraChan1046 · 6 May 2026, 14:28 UTC

Reply to discussion
CL
ClaraChan1046
Reviewing bracket records for a UR5e proposal. Aligned while restrained, out after release. Archive kept untouched. Which comparisons are defensible?

20 replies

BE
BethBennett0759
Replying to ClaraChan1046

On a review I helped with, apparently paired readings came from different pieces. First establish which identified bracket each note describes, its revision and the measurement condition. Keep the uncertain links uncertain rather than making a neat sequence out of them.

20 points
CL
ClaraChan1046
Replying to BethBennett0759

Some notes only identify the batch. One route card does name a particular bracket.

14 points
DA
DavidAbbott0084
Replying to ClaraChan1046

I would start with that card, not average the batch notes into a story about it. We found a retained sample from a later run sitting beside earlier inspection sheets once. Perfectly real records, wrong comparison.

6 points
HA
HarishAllen0315
Replying to ClaraChan1046

Does aligned mean a measured result on that card, or a visual setup observation? Those could be quite different kinds of evidence.

9 points
CL
ClaraChan1046
Replying to HarishAllen0315

Visual observation. There is a separate angle reading, with no measurement method written beside it.

16 points
JA
JaneArcher0423
Replying to ClaraChan1046

Then don't price the new fixture as reproducing that angle. You haven't established what it measures yet.

5 points
LI
LiamChen1186
Replying to JaneArcher0423

And who is allowing for the correction labour in the proposal?

6 points
AM
AmyBaker0467
Replying to JaneArcher0423

Jane's point doesn't require throwing the reading away; it can stay in the review as an observation whose method still needs explaining, rather than a target somebody should reproduce

25 points
BE
BethBennett0759
Replying to ClaraChan1046

Can the original inspector identify that method while they're still available? It might be easier to ask about one particular card than hand them the entire folder and ask what used to happen.

6 points
CL
ClaraChan1046
Replying to BethBennett0759

They identified two setups. Restrained reading used the fixture face. Released inspection used the drawing datum arrangement.

16 points
DA
DavidAbbott0084
Replying to ClaraChan1046

That explains why subtracting the two numbers would be a dubious shortcut. Do you have enough recorded geometry to relate the setups, or only the readings?

12 points
HA
HarishAllen0315
Replying to DavidAbbott0084

Ask the measurement owner to establish that relationship. Or, if the information is missing, state that the historical change cannot be calculated from these notes alone.

6 points
CL
ClaraChan1046
Replying to HarishAllen0315

Only readings survive. Quality won't translate them into a release change. That comparison stays unavailable.

16 points
AM
AmyBaker0467
Replying to ClaraChan1046

You can still report the released nonconformance against its documented requirement, if quality confirms that record; unavailable change isn't the same as no evidence of a problem

7 points
LI
LiamChen1186
Replying to ClaraChan1046

So can the new estimate carry a stated allowance pending the trial?

15 points
JA
JaneArcher0423
Replying to LiamChen1186

Liam, why are we back to a price before the trial scope is defined? That's how the missing work becomes someone's free afternoon.

16 points
LI
LiamChen1186
Replying to JaneArcher0423

Not a guessed fixture price. An explicit uncertain allowance, with the study priced separately. Should've said that.

9 points
BE
BethBennett0759
Replying to LiamChen1186

The study can specify the missing evidence now: identified incoming pieces and fit-up, documented fixture condition, then released measurements under the agreed method. The welding and measurement specialists need to set that scope. None of that requires pretending the old figures answer it.

8 points
CL
ClaraChan1046
Replying to BethBennett0759

Agreed sample plan requested from both specialists. Cost uncertainty remains explicit. No live welding changes made during this records review.

19 points
DA
DavidAbbott0084
Replying to ClaraChan1046

Does the plan keep any later correction and reinspection identifiable too? You don't want the next retained sample to lose the same part of its history.

4 points

Add to the discussion

Welcome to Application Robot

Everyone can read the forum. Sign in or create an account to start a discussion, reply, or upload photos.

Forgot your password?

By creating an account, you agree to our Terms and Conditions and community guidelines. Read our Privacy Policy for how your information is handled.