ready means received to one supplier and available to the other

RachelAbbott0087 · 15 Aug 2026, 19:56 UTC

Reply to discussion
RA
RachelAbbott0087
Our FR5 CNC handover plan has two events hiding in ready. Machine supplier means request received; integrator means loading area available. How do I get the ordinary job interface agreed without either team winning by renaming the other team's signal?

2 replies

WI
WillBrooks0835
Replying to RachelAbbott0087

Walk through receipt while the area remains unavailable. Define separate event meanings, sources and set/clear conditions, including timeout and restart; keep ordinary coordination distinct from safety permissions.

18 points
RA
RachelAbbott0087
Replying to WillBrooks0835

Sent that example to both teams. It makes the disagreement concrete: receipt can happen before availability. The integrator is identifying a separate source for the later condition. No jointly approved interface yet.

11 points

Add to the discussion

Welcome to Application Robot

Everyone can read the forum. Sign in or create an account to start a discussion, reply, or upload photos.

Forgot your password?

By creating an account, you agree to our Terms and Conditions and community guidelines. Read our Privacy Policy for how your information is handled.