The seller in China confirmed our fixture drawing before we ordered the UR5e configuration. Delivery has a different label suffix and a visibly different interface around the flange adapter. Twenty-one days awaiting their comparison. Tooling remains unfitted; I need evidence of applicability, not a general equivalence assurance.
Separate the label difference from the interface difference in your enquiry. The suffix may have an explanation that says nothing about whether your tooling fits the adapter they actually supplied.
Keep the confirmed drawing revision beside the delivery views. Similarity to a catalogue picture will not establish which configuration they agreed to supply.
The receipt names the arm but gives no separate adapter reference. I've sent the confirmed drawing revision and marked the visible locating-face difference without trying to fit our tooling.
Have your tooling reviewer name the relevant locating, fastening and resulting tool-position requirements. That gives the seller a concrete comparison to answer, and may reveal differences that a front photograph cannot show.
Our reviewer has listed those requirements, including the locating shoulder and clearance behind the plate. Seller says the suffix is a supply revision, but still has not identified the adapter drawing.
A technical contact has now supplied the delivered adapter drawing. Our reviewer found its shoulder conflicts with the recess in our confirmed fixture interface; it is not suitable as supplied for this tool.
That is the finding to put back to the seller. Ask them to propose how they will meet the confirmed interface, with the technical comparison and any commercial terms explicit; do not silently turn it into your workshop's modification job.
They proposed supplying a different adapter. It has not shipped, and I have asked for its drawing before accepting the proposal. No agreement to modify our fixture.
Not yet. Those are on the reviewer list with the load implications and fastening details. Thanks, Amy; we have a specific confirmed mismatch now, but the replacement proposal still needs assessment and agreed supply terms.