My FR10 tray-loading estimate missed fixture design and our own staff time. My colleague is fed up with the moving total. How small can we make a pilot that actually tests those costs?
We have one mounting block that runs most weeks. I can limit the pilot to that, but it arrives loose in a box. Presentation is probably the expensive unknown
Our class once timed the easy tray ten times and called it representative, then discovered the person supplying those trays was doing all the hard work off camera.
She picked the sample with the operator. It includes normal tangled arrivals and a tray change. We've agreed to report assistance separately instead of hiding it in a cycle average
Cannot judge the saving without a baseline. Time the current method on comparable work as well, and note interruptions rather than quietly deleting them.
We agreed an effort cap at the planning meeting. No arm order from this exercise; the next decision is whether presentation is worth a paid tooling trial