I pulled the original travellers for the support brackets in our FR10 estimate. The restrained alignment tick is followed by a released dimensional failure. Later sheets show a pass. The estimate calls everything between those points 'correction'. There is a fitting-bench visit in there, but also a planned machining operation that already appears elsewhere in the cost. I want the real correction explained, not deleted because one line is duplicated. The bracket identities and drawing revision match. The operation descriptions are the untidy bit.

19 replies

HA
HarishChen1185
Replying to AnnaArcher0416

Keep the original route beside the estimate. Which feature failed at the first released check? That should help distinguish correction of the welded shape from the machining already planned.

4 points
AN
AnnaArcher0416
Replying to HarishChen1185

Mounting-face angle. Planned machining is the clearance holes. Final sheet records both, but the summary treats the whole interval as angle correction.

-2 points
AN
AnnaBennett0764
Replying to AnnaArcher0416

So the machining duplicate can be removed once the estimator confirms where it is already charged. The angle failure still needs its own route. I wouldn't discount that work just because the summary is poor.

17 points
AD
AdaBarnes0564
Replying to AnnaArcher0416

Does the fitting-bench entry actually say straightening?

7 points
JA
JasperBaker0464
Replying to AnnaArcher0416

And can the person who did that work link their explanation to this bracket group, rather than describe what generally happens at that bench?

8 points
AN
AnnaArcher0416
Replying to JasperBaker0464

Entry says angle corrected. Supervisor traced it to the fitter, who has a note for these same bracket references. He straightened them before the final angle check. No individual times.

17 points
HA
HarishChen1185
Replying to AnnaArcher0416

That explains the operation. Do the two angle checks use the same support method?

19 points
AN
AnnaBennett0764
Replying to HarishChen1185

Harish, yes. A final pass on another setup would leave an extra measurement question even with the straightening confirmed.

3 points
AD
AdaBarnes0564
Replying to AnnaBennett0764

Ours did exactly that. Different supports, same reassuring word 'pass'.

3 points
AN
AnnaArcher0416
Replying to HarishChen1185

Quality checked the methods. Same support and angle requirement for these two results. The first sheet is before straightening and the final angle result after it; the hole check is a separate entry.

9 points
JA
JasperBaker0464
Replying to AnnaArcher0416

Give the estimator those separate operations now, even if the remaining labour allowance still needs an observation.

1 points
HA
HarishChen1185
Replying to AdaBarnes0564

Ada, did yours have any matching recheck hidden elsewhere? I nearly missed one because it was filed with the outgoing inspection rather than the correction sheet.

2 points
AN
AnnaArcher0416
Replying to JasperBaker0464

Estimator removed the duplicated hole machining. Straightening and reinspection remain separate allowances. We are observing a current manual group to replace the guesswork on time.

11 points
AN
AnnaBennett0764
Replying to AnnaArcher0416

Include the inspection queue in elapsed time, but do not book every waiting minute as the fitter's hands-on labour. That distinction can affect staffing as much as the correction itself.

5 points
AD
AdaBarnes0564
Replying to HarishChen1185

Harish, no matching old recheck yet. We've stopped using that comparison for a correction allowance.

9 points
JA
JasperBaker0464
Replying to AnnaArcher0416

Anna Archer, is the current group the same bracket revision and route as your historical example?

4 points
AN
AnnaArcher0416
Replying to JasperBaker0464

Same bracket revision, changed inspection location. We kept that change explicit. Observation finished: fitter work, movement and inspection waiting are separate now, and the changed walking route is priced for the proposed location.

12 points
HA
HarishChen1185
Replying to AnnaArcher0416

Useful. What happened to the incoming fit-up work? I cannot tell whether it was included before the restrained alignment tick or omitted from the old costing too.

5 points
AN
AnnaArcher0416
Replying to HarishChen1185

It was charged under preparation, and the estimator has kept it there. We have corrected this cost breakdown without assuming a new FR10 fixture eliminates straightening. The fixture designer still needs to address why this bracket group required it.

13 points

Add to the discussion

Welcome to Application Robot

Everyone can read the forum. Sign in or create an account to start a discussion, reply, or upload photos.

Forgot your password?

By creating an account, you agree to our Terms and Conditions and community guidelines. Read our Privacy Policy for how your information is handled.