our ur5e packing total has blank lines where the work is

NathanBarnes0547 · 25 Dec 2025, 10:08 UTC

Closed
NA
NathanBarnes0547
The UR5e packing quote now includes the arm, gripper and one training session; fixtures, guarding and the next carton changeover are still blank, so how do I compare it without treating blank as free?

5 replies

IS
IsabelChen1170
Replying to NathanBarnes0547

Separate confirmed prices, stated allowances and unpriced scope. Give each unknown an owner and the information needed to price it. Both suppliers should describe the same packing tasks, including preparation and changeover, before their totals are compared.

16 points
NA
NathanBarnes0547
Replying to IsabelChen1170

One assumes we supply the carton guides and the other includes one set; neither names which kit variant the training uses.

13 points
IS
IsabelChen1170
Replying to NathanBarnes0547

Name the guide variants and operator tasks in the enquiry. Ask what the session enables your staff to do, who attends and what further support is excluded. One session alone does not describe the handover.

10 points
NA
NathanBarnes0547
Replying to IsabelChen1170

Both enquiries now name our two regular kit variants and both shifts; the total is still provisional, but at least the missing guide work has a person beside it.

6 points
IS
IsabelChen1170
Replying to NathanBarnes0547

Has that person agreed to supply the work within a stated allowance, or are they only responsible for obtaining the missing estimate? Keep those roles distinct when you circulate the total.

4 points

Discussion closed

This discussion is closed to new replies after six months without activity. Last activity: .