our ur5e handover stops at a subprogram nobody included

DineshBrooks0821 · 14 Jan 2026, 17:03 UTC

Closed
DI
DineshBrooks0821
I followed our inspection screenshots until the main routine called a subprogram that is absent from the handover. The integrator is still available. I want to trace one bracket through the whole job with our relief maintainer, including what happens when its result is missing.

17 replies

YA
YasminBarnes0528
Replying to DineshBrooks0821

Start with that missing call. Ask for the matching program package and a list of the external signals it uses. Your screenshots can illustrate it afterwards; they cannot tell your relief maintainer what code was omitted.

24 points
DI
DineshBrooks0821
Replying to YasminBarnes0528

The integrator says the subprogram waits for inspection complete and then files the result. There are two similarly named versions in the backup folder. I have asked which one belongs to the installed main routine.

22 points
DA
DavidBarnes0606
Replying to DineshBrooks0821

Ask what inspection complete actually means there, because receiving a result and accepting the bracket aren't necessarily the same event

7 points
JA
JackAllen0341
Replying to DineshBrooks0821

Our inherited backup folder had a final and a final-new. Neither matched the running job. Get the installed package identified first. The filenames were the most confident part of our handover.

15 points
YA
YasminBarnes0528
Replying to JackAllen0341

And preserve both old copies separately. It is tempting to tidy the folder before anyone has worked out why there are two. You want a known current package, not a neat folder with the evidence thrown away.

14 points
DI
DineshBrooks0821
Replying to DavidBarnes0606

Integrator identified the installed package and supplied its matching export. The extra subprogram belongs to an abandoned trial. David, complete means a result was received; acceptance is a field in that result, which the screenshots never show.

20 points
SA
SaraArcher0374
Replying to DineshBrooks0821

Will the relief maintainer get time to work through it before the integrator leaves? Give that person a slot, not an invitation to read it between faults.

25 points
JA
JackAllen0341
Replying to SaraArcher0374

Sara's right. We tried the between-faults version. Three weeks later everyone had read page one and the original programmer had moved on. A short booked session would have cost less than the calls afterwards.

16 points
DI
DineshBrooks0821
Replying to SaraArcher0374

We have booked the session. The relief maintainer wants to follow a normal result and a missing result first, then a held bracket. I had only proposed the normal case, so that is already a useful change.

25 points
DA
DavidBarnes0606
Replying to DineshBrooks0821

Let inspection explain the held bracket, since I wouldn't want a maintainer inferring its release rules from a field name

22 points
YA
YasminBarnes0528
Replying to DineshBrooks0821

Give the maintainer the documents and let them lead. If the integrator has to point at every next step, you've tested the integrator's memory again.

7 points
SA
SaraArcher0374
Replying to DineshBrooks0821

Who is covering the maintainer's ordinary calls during that session?

7 points
DI
DineshBrooks0821
Replying to SaraArcher0374

The day lead covered the calls. In the read-through our relief maintainer found the missing-result page told them to clear a request without first establishing whether a result already existed. The integrator has withdrawn that instruction and is correcting the recovery section.

13 points
JA
JackAllen0341
Replying to DineshBrooks0821

That's exactly the sort of omission a normal run won't expose. Did the held-bracket case make sense without help?

15 points
DI
DineshBrooks0821
Replying to JackAllen0341

It did after inspection named the disposition owner. The maintainer could explain that the completed inspection did not authorise a held bracket to leave the hold process. The operator page now uses that wording too.

24 points
DI
DineshBrooks0821
Replying to DineshBrooks0821

The second read-through passed with the corrected recovery section. We used the agreed offline cases, including an already existing result after an interruption; the maintainer followed the reconciliation and escalation without prompting. Maintenance also verified the current export against the installed package. I've accepted this handover revision.

6 points
YA
YasminBarnes0528
Replying to DineshBrooks0821

Good. Keep the actual cases with it for the next relief maintainer. They're more useful than a signature saying somebody once understood the folder.