Why does our nearly finished FR10 housing total include reviewed retries?

DanielAli0217 · 25 Aug 2026, 00:51 UTC

Reply to discussion
DA
DanielAli0217
We planned 167 housings. FR10 dashboard includes repeated inspections after restart. I need unique accepted housings without deleting failed attempts.

20 replies

CA
CalebCarter1015
Replying to DanielAli0217

What identifies a housing independently of an inspection attempt?

15 points
EL
ElenaBennett0775
Replying to DanielAli0217

And how many messages are just repeated delivery of one attempt?

12 points
OW
OwenAllen0312
Replying to ElenaBennett0775

Keep those as three levels: the physical housing, its inspection attempts, and delivery of each result. Removing repeated messages should not remove a genuine reviewed reinspection, but neither should a reinspection manufacture another housing.

0 points
DA
DanielAli0217
Replying to OwenAllen0312

Housing and attempt identities survive restart. Display says 164; we are checking deliveries against the stored attempts.

3 points
EL
EllaChan1077
Replying to DanielAli0217

Who owns the current disposition when a housing has more than one attempt? I would want quality's rule before a developer chooses first pass, last arrival or any other convenient interpretation.

11 points
CA
CalebCarter1015
Replying to EllaChan1077

And leave the failed attempt readable. Someone will eventually ask why that accepted housing was reinspected.

8 points
DA
DanielAli0217
Replying to DanielAli0217

Reconciliation found 158 distinct attempts on 151 housings. Seven reinspections, plus six repeated result deliveries in the displayed 164.

3 points
EL
ElenaBennett0775
Replying to DanielAli0217

So 151 inspected is not yet your accepted count.

3 points
OW
OwenAllen0312
Replying to ElenaBennett0775

Exactly. Ask quality to classify those 151 by the authoritative disposition records. The remaining sixteen planned housings have no inspection attempt in this reconciliation; don't silently classify them as failed.

10 points
DA
DanielAli0217
Replying to OwenAllen0312

Quality reports 143 accepted, five held and three rejected among the 151. Sixteen uninspected remains separate.

10 points
EL
EllaChan1077
Replying to DanielAli0217

Does the accepted list include the housings whose reviewed retry passed? Otherwise the new total could be unique but still ignore the permitted disposition changes you wanted to preserve.

22 points
DA
DanielAli0217
Replying to EllaChan1077

Yes. Quality linked each reviewed retry to its housing and retained the original failed result. No attempt erased.

21 points
CA
CalebCarter1015
Replying to DanielAli0217

What will the next shift see instead of nearly done?

10 points
DA
DanielAli0217
Replying to CalebCarter1015

Proposed screen shows 143 accepted of 167 planned, with held, rejected and uninspected counts alongside; developer is rebuilding from disposition records.

12 points
OW
OwenAllen0312
Replying to DanielAli0217

Test delayed delivery of an older failed attempt after its reviewed successful retry. Arrival order should not reverse an authorised disposition merely because an old message came in last. Also test genuinely missing disposition evidence as unknown, not accepted.

19 points
EL
ElenaBennett0775
Replying to OwenAllen0312

What about a new failed check after acceptance?

6 points
DA
DanielAli0217
Replying to ElenaBennett0775

Quality defined that as review-required hold, not automatic continued acceptance. Tests now include both older delayed failure and genuinely later failure.

9 points
EL
EllaChan1077
Replying to DanielAli0217

Has the corrected screen survived reopening from the saved records? A display adjusted by subtracting six repeats could look right once and still return the old total on launch.

10 points
DA
DanielAli0217
Replying to EllaChan1077

Reopen and replay checks passed. Reviewed report now rebuilds as 143 accepted, five held, three rejected, sixteen uninspected. Shift lead has the corrected total and original inflated report.

16 points
CA
CalebCarter1015
Replying to DanielAli0217

Thanks for the breakdown. The twenty-four not accepted are now visible without calling them twenty-four failed housings.

2 points

Add to the discussion

Welcome to Application Robot

Everyone can read the forum. Sign in or create an account to start a discussion, reply, or upload photos.

Forgot your password?

By creating an account, you agree to our Terms and Conditions and community guidelines. Read our Privacy Policy for how your information is handled.