Draw what was captured first. PLC request edge, application reads, then any acknowledgement. Don't draw the acknowledgement where someone says it ought to be
Unowned request clearing at the inspection station
MinaArcher0424 · 8 Jun 2026, 19:46 UTC
I need the request clearing agreed before commissioning our FR5 coupon inspection station. The application misses brief PLC requests, and the interface notes assign no clear owner. Separate safety system. Has anyone used a simple timing sketch to get the two software authors to describe what they actually send?
4 replies