our ur5e pilot budget borrowed the fixture maker

ZaraBaker0482 · 5 Jan 2026, 02:33 UTC

Closed
ZA
ZaraBaker0482
I priced a UR5e and gripper for mounting-block loading, then asked my colleague for fixture help as though that had no cost. She wants the trial bounded before her team is committed. I need a small study we can judge together, with their time included from the start.

4 replies

LU
LuisBarnes0608
Replying to ZaraBaker0482

Start with the uncertainty that could stop the idea before a fixture is built. Define representative blocks, the current loading work and a limited review deliverable. Put preparation and attendance beside the supplier's price.

11 points
ZA
ZaraBaker0482
Replying to LuisBarnes0608

The uncertain part is release into the existing nest without the setter repositioning the block. We have two regular variants. I have asked for a sample-and-drawing review of that task, not a working cell promised at the end.

12 points
LU
LuisBarnes0608
Replying to ZaraBaker0482

Give that review an end where both of you can stop. A list of further options is a deliverable, not permission to spend another month making the first one work.

23 points
ZA
ZaraBaker0482
Replying to LuisBarnes0608

Agreed with my colleague. Both variants and the present setter intervention are included, with capped preparation time and a joint decision after the findings. Fixture manufacture and a robot trial are separate, unapproved next steps. Thanks Luis.

17 points