Both suppliers ticked ready while describing different events

AdamBlair · 17 Oct 2025, 07:29 UTC

Closed
AD
AdamBlair
I put our proposed UR5e bush-loading sequence in a shared table. Both suppliers ticked the ready column, which looked promising until one explained it meant request received and the other meant the loading area was available. We have agreed on a word and almost nothing behind it.

19 replies

MA
MayaBarnes0562
Replying to AdamBlair

What does each team expect the other side to do when ready turns on?

11 points
RE
RebeccaBarnes0604
Replying to AdamBlair

Can you draw the sequence with event names instead of signal names? I would take ready off the first draft altogether.

-2 points
SA
SamBaker0507
Replying to AdamBlair

Who clears it?

24 points
YA
YasminAdams0093
Replying to RebeccaBarnes0604

Rebecca's approach helped us untangle a similar table, though we still needed the eventual signal names alongside it for maintenance to follow the screen.

8 points
AD
AdamBlair
Replying to MayaBarnes0562

Maya, one team expects us to wait after ready and the other expects the sequence to proceed. Sam, they also disagree about who clears it. Rebecca's event-only version may save us another meeting about the spelling.

22 points
MA
MayaBarnes0562
Replying to YasminAdams0093

Yasmin, yes, event wording first and screen wording beside it once the meanings agree.

16 points
RE
RebeccaBarnes0604
Replying to AdamBlair

Adam, what happens to an accepted request when communication drops? That is where our tidy drawing fell apart.

21 points
SA
SamBaker0507
Replying to RebeccaBarnes0604

Was yours forgotten, Rebecca, or repeated?

1 points
RE
RebeccaBarnes0604
Replying to SamBaker0507

Repeated in the software test. The receiver remembered accepting it, but the sender restarted as though nothing had happened. We needed the controls people to sort that out, not another label.

16 points
AD
AdamBlair
Replying to RebeccaBarnes0604

Rebecca, ours has a blank box for communication loss. I had treated that as a later detail. Your example is useful; I have added it to the supplier discussion alongside the normal loading sequence.

13 points
YA
YasminAdams0093
Replying to AdamBlair

A blank box is easy to overlook when the normal path fills a page, and the operator will meet that box without the two suppliers beside them.

13 points
MA
MayaBarnes0562
Replying to AdamBlair

Also, request received must not be treated as permission to enter the machine area.

23 points
AD
AdamBlair
Replying to MayaBarnes0562

Agreed, Maya. We are calling it request accepted in the discussion copy and keeping the access conditions separate. Neither team has signed the revised sequence, so these are proposed meanings, not a commissioned interface.

15 points
RE
RebeccaBarnes0604
Replying to MayaBarnes0562

Maya, would you put the access conditions on the same drawing? Ours became hard to read once every dependency was squeezed in.

24 points
MA
MayaBarnes0562
Replying to RebeccaBarnes0604

Linked detail is fine, Rebecca, as long as the sequence points to it unambiguously.

4 points
SA
SamBaker0507
Replying to AdamBlair

Adam, is there a request identifier in the proposal?

17 points
YA
YasminAdams0093
Replying to SamBaker0507

Sam, I would let their controls teams choose the mechanism, but I do want them to explain how a delayed answer is matched to the request it belongs to.

-2 points
AD
AdamBlair
Replying to YasminAdams0093

Sam and Yasmin, nothing has been chosen for matching requests yet. I have asked for a worked example with a delayed answer after reconnect. Thanks Rebecca for the restart story; it made the missing case much easier to explain.

8 points
RE
RebeccaBarnes0604
Replying to AdamBlair

Good. Ask them to walk it from both ends. We each thought the other application was retaining the bit that mattered.

25 points