How should I compare sleeve transfers when one supplier changes the tray?

IsabelChen1170 · 12 Feb 2026, 06:45 UTC

Closed
IS
IsabelChen1170
I am willing to change the tray for our UR5e proposal if it improves the complete sleeve-loading job. One demo uses dedicated pockets and the other uses our existing tray. I need preparation, changeover and unsuitable sleeves included before comparing the apparent speed.

1 reply

LU
LuisBarnes0608
Replying to IsabelChen1170

Ask where the unsuitable sleeves go and who decides they cannot run. A reject pocket without that decision can quietly become another sorting job for your operator.