Existing fixture loading station: Different label suffix, different mounting arrangement

MeiChan1125 · 3 Sept 2026, 00:44 UTC

Reply to discussion
ME
MeiChan1125
I ordered Fairino FR10 from an unnamed seller in China after they confirmed a configuration against our fixture drawing. The delivered label has a different suffix, and the interface around the tool interface bracket looks different from that drawing. The seller says equivalent but hasn't provided a comparison. I've left our tooling unfitted and waited 23 days for clarification. We're working at an existing fixture loading station.

10 replies

JA
JasperAbbott0029
Replying to MeiChan1125

@MeiChan1125 Do you've the seller's confirmation, delivered identification label, and fixture drawing available together? Comparing those would identify the discrepancy without assuming what the suffix means.

16 points
ME
MeiChan1125
Replying to JasperAbbott0029

I've the prepayment confirmation referring to our drawing and the different delivered identifier. Our unpacking photographs also show the interface as received, with no tooling installed.

8 points
JA
JasperAbbott0029
Replying to MeiChan1125

@MeiChan1125 Send that comparison and ask for the applicable interface drawing for the delivered configuration. Leave the tooling unfitted while compatibility is checked.

20 points
ME
MeiChan1125
Replying to JasperAbbott0029

Can I describe this as the wrong revision based on the suffix alone? I'd prefer not to make the dispute depend on an unverified interpretation of the identifier.

11 points
RO
RobinArcher0425
Replying to MeiChan1125

Call it a configuration discrepancy. Quote both identifiers and show the visible interface difference. That gives them two concrete things to explain.

16 points
JA
JasperAbbott0029
Replying to RobinArcher0425

A matching interface drawing would establish that the delivered configuration is compatible with your fixture. Request that document to support the seller's equivalence claim.

12 points
HA
HanaAbbott0013
Replying to JasperAbbott0029

@JasperAbbott0029 The interface drawing could address physical fit, but it wouldn't by itself establish compatibility for all connections and application requirements.

15 points
JA
JasperAbbott0029
Replying to HanaAbbott0013

I overstated what that document would establish. The drawing can help resolve physical fit, while the remaining compatibility questions need assessment against your intended configuration and application.

15 points
ME
MeiChan1125
Replying to JasperAbbott0029

I've accepted the delivered interface after a completed configuration comparison and qualified review against our stated fixture requirements. That resolves this discrepancy for us, with installation checks still required.

19 points
JA
JasperAbbott0029
Replying to MeiChan1125

Your stated fixture requirements now have supporting review, and you've kept the outstanding installation work clear.

21 points

Add to the discussion

Welcome to Application Robot

Everyone can read the forum. Sign in or create an account to start a discussion, reply, or upload photos.

Forgot your password?

By creating an account, you agree to our Terms and Conditions and community guidelines. Read our Privacy Policy for how your information is handled.