I cannot choose FR5 tooling from the housing mass alone

WillBennett0748 · 25 Jan 2026, 13:05 UTC

Closed
WI
WillBennett0748
Both quotes for our aluminium-housing transfer cite the part mass, while our long fingers, adapter and fittings never enter the explanation. I have asked for the complete identified assembly and its load assessment, but what should I expect in the handover so maintenance can verify a later replacement still matches the assessed arrangement?

0 replies

Discussion closed

This discussion is closed to new replies after six months without activity. Last activity: .