I am comparing two FR5 tooling proposals for machined aluminium housings. Each suitability statement uses the housing mass alone. Both arrangements also have extended fingers, an adapter and hose fittings. What evidence should I require for the complete assembly before purchasing?

10 replies

EM
EmmaBarnes0550
Replying to DineshBarnes0560

Our layout review once lengthened an adapter to clear a fixture without updating the load assessment. Get the actual assembled proposal identified first: masses, centres of mass, geometry and relevant load information for the intended motion. The responsible supplier should assess it against the applicable robot and tooling limits, not give you a verdict about an isolated housing.

13 points
GR
GraceAdams0146
Replying to DineshBarnes0560

Ask what each price actually includes too. Their suitability diagram and supplied parts list may not describe the same fingers or adapter.

23 points
OS
OscarAli0184
Replying to EmmaBarnes0550

And who owns the assessment when one supplier provides the hand and another the adapter?

7 points
DI
DineshBarnes0560
Replying to GraceAdams0146

One proposal lists the adapter as customer supplied. Its sketch still shows it. I had assumed a pictured item was included in both the price and assessment.

5 points
EM
EmmaBarnes0550
Replying to DineshBarnes0560

Then that offer needs an explicit interface and assessment responsibility for your adapter. Customer supplied does not mean it can be absent from the assembled load case. It also leaves you responsible for obtaining its actual data rather than letting the illustration supply imaginary dimensions.

8 points
HA
HassanChen1139
Replying to EmmaBarnes0550

Could the extended fingers change again after they review fixture access? Sounds like a moving purchase target unless that layout is identified too.

9 points
GR
GraceAdams0146
Replying to HassanChen1139

I wouldn't insist every detail is frozen before a quotation. But the quotation must say which arrangement it covers and what would trigger a revised assessment and price.

4 points
DI
DineshBarnes0560
Replying to EmmaBarnes0550

The first supplier will assess the complete assembly once we provide the adapter data. The second has supplied its assembled drawing and identified an unresolved finger-extension requirement. Neither offer is approved for purchase yet.

23 points
OS
OscarAli0184
Replying to DineshBarnes0560

That leaves two defined questions instead of two unsupported yeses. Has someone taken the adapter measurement job?

4 points
DI
DineshBarnes0560
Replying to OscarAli0184

Tooling has it, including the arrangement used for the access study. Grace's point also corrected my comparison: the first offer no longer appears to include an adapter we would have to supply.

4 points

Add to the discussion

Welcome to Application Robot

Everyone can read the forum. Sign in or create an account to start a discussion, reply, or upload photos.

Forgot your password?

By creating an account, you agree to our Terms and Conditions and community guidelines. Read our Privacy Policy for how your information is handled.