Every addition moves my carton-cell estimate further from the arm quote

SaraBarnes0548 · 23 Aug 2026, 04:30 UTC

Reply to discussion
SA
SaraBarnes0548
My UR5e carton-insert estimate now needs presentation fixtures, guarding and training. Several amounts remain unknown. How can I compare complete proposals without those blanks quietly becoming zero?

12 replies

JO
JonasArcher0372
Replying to SaraBarnes0548

Give each blank an owner and a scope description. Don't total two proposals as equivalent when one hasn't priced the work.

16 points
HA
HassanBennett0704
Replying to JonasArcher0372

I'd show the known subtotal, then the unresolved items underneath. Or perhaps ranges, if somebody can explain where the limits come from. A guessed allowance displayed to the penny will look more settled than it is.

4 points
LO
LouisBarnes0572
Replying to SaraBarnes0548

Training needs content, too. Mine covered start-up but left every interruption with me. Price the handover you actually need.

24 points
JO
JonasArcher0372
Replying to HassanBennett0704

Ranges won't repair different scope, Hassan. One supplier may assume hand-presented cartons while another includes the preparation fixture.

1 points
SA
SaraBarnes0548
Replying to JonasArcher0372

That is exactly the split. One proposal starts with an oriented carton already held in place. I had compared its total with a proposal that includes presentation.

8 points
HA
HassanBennett0704
Replying to SaraBarnes0548

Then I would sort that before estimating the gap. Can the first supplier price the same starting condition, or are they offering a deliberately smaller job? Both are legitimate offers, just not substitutes in your current comparison.

16 points
SA
SaraBarnes0548
Replying to HassanBennett0704

I sent both the same starting and finishing conditions. The first supplier will price the presentation work separately. Training now includes our specified interruption handover, not just a session duration.

14 points
LO
LouisBarnes0572
Replying to SaraBarnes0548

Who supplies replacement presentation parts? The first fixture price doesn't tell maintenance what a damaged contact costs or who can make it.

16 points
JO
JonasArcher0372
Replying to LouisBarnes0572

Keep that visible, but don't hold up the basic comparison for a lifetime-cost prediction nobody can support. Separate the initial scope and known recurring provisions.

14 points
HA
HassanBennett0704
Replying to JonasArcher0372

Yes, a separate line is enough for now. Sara can compare the initial offers and still say that replacement pricing is unconfirmed. That is more useful than folding an invented annual repair bill into either total.

17 points
SA
SaraBarnes0548
Replying to HassanBennett0704

Revised prices arrived. With presentation included, the apparently cheaper offer is higher. Both now price the same defined work; replacement-part pricing remains outside the initial comparison and visibly unconfirmed.

11 points
SA
SaraBarnes0548
Replying to LouisBarnes0572

I have issued the corrected comparison and withdrawn the old arm-price ranking. No purchase decision yet. Louis, your training example caught a real omission in my scope, thanks.

8 points

Add to the discussion

Welcome to Application Robot

Everyone can read the forum. Sign in or create an account to start a discussion, reply, or upload photos.

Forgot your password?

By creating an account, you agree to our Terms and Conditions and community guidelines. Read our Privacy Policy for how your information is handled.