Cannot connect this FR10 motion clip to our agreed housing-handling demonstration

LeahBennett0756 · 4 Jul 2026, 16:39 UTC

Reply to discussion
LE
LeahBennett0756
Our agreed pre-shipment check uses the specified contact pads and molded housings. After thirty-five days, the seller's clip still lacks package identity and clear handling views. What would make the next recording answer that agreement?

15 replies

LE
LeoAdams0101
Replying to LeahBennett0756

Which package and tooling identifiers are actually visible in the clip, Leah? I'd separate missing identity from missing views of the agreed handling.

18 points
LE
LeahBennett0756
Replying to LeoAdams0101

No readable package or pad-set identifiers. Pickup is distant and the destination is outside the view. I've requested order-linked equipment identification and the complete agreed transfer, not another general motion recording.

15 points
GR
GraceAdams0146
Replying to LeahBennett0756

Keep that request tied to the agreed demonstration scope. I wouldn't call an unrelated clip a failed sample test either; it hasn't shown the agreed test happening.

18 points
AI
AishaBell0692
Replying to LeahBennett0756

I've inherited tooling where the pictured spare belonged to another revision, despite the main assembly looking familiar. Ask the seller to identify the fitted contact-pad set in the demonstration, not merely put the correct arm label at the start of a film. Maintenance will need that distinction after delivery too.

20 points
VI
VictorBaker0446
Replying to LeahBennett0756

Does the agreed task define what successful placement and release should show, including the receiving arrangement, so the next camera view can be assessed against something more specific than the housing arriving nearby?

21 points
AA
AaronAllen0262
Replying to VictorBaker0446

The receiving view matters in my request too; a fixture screen hides our contact and the tray is out of frame, so I cannot tell whether the recorded motion completed the handling we agreed

7 points
CH
ChloeAli0222
Replying to AaronAllen0262

Aaron, that is a visibility gap even if the equipment is identified. Leah has both gaps, so I would not let a readable serial in the next clip count as the handling answer as well

2 points
AL
AlexCarter0994
Replying to VictorBaker0446

Include any manual preparation or intervention used during the agreed demonstration. It is part of the observed method.

23 points
LE
LeahBennett0756
Replying to LeahBennett0756

The next recording identifies our package and fitted pads, but the receiving fixture still hides release. Victor, the agreement specifies seating in that fixture; Alex Carter, manual sample preparation is visible and matches the agreed condition.

8 points
AN
AnnaChan1112
Replying to LeahBennett0756

Could a second linked view show release at the fixture? Not another unrelated close-up, but a view that belongs to the same identified setup and handling result.

5 points
AL
AlexChen1168
Replying to AnnaChan1112

A second view can answer that without anyone changing the protective arrangement for a better film. Ask the demonstrator to plan the recording under their normal authorised test conditions. Camera convenience is not a reason to improvise the setup or conceal an intervention.

17 points
AI
Aileen_Burke
Replying to AnnaChan1112

If they send separate views, keep the link to the same samples, tool revision and stated test conditions explicit; I would find that more useful than one polished montage where a close-up could come from a different run without anybody noticing.

7 points
LE
LeahBennett0756
Replying to AnnaChan1112

The linked second view now shows the agreed housings seated and released into the identified fixture, with the same pad assembly and preparation. Our technical reviewer matched it to the demonstration scope; that missing handling item is now accepted.

18 points
CA
CallumAbbott0012
Replying to LeahBennett0756

Does that acceptance cover only the agreed pre-shipment demonstration? I would keep receipt checks and installation assessment separate, so a good recording does not become a claim about the setup after transport.

13 points
LE
LeahBennett0756
Replying to CallumAbbott0012

Yes, Callum. Only the defined pre-shipment sample check is closed. The accepted record identifies its limits and configuration; receipt, installed assessment and the rest of the purchase obligations have not been marked complete.

9 points

Add to the discussion

Welcome to Application Robot

Everyone can read the forum. Sign in or create an account to start a discussion, reply, or upload photos.

Forgot your password?

By creating an account, you agree to our Terms and Conditions and community guidelines. Read our Privacy Policy for how your information is handled.