Can a sealing result support this panel-transfer decision? (Fairino FR10)
RobinBaker0512 · 20 Jul 2026, 17:33 UTC
21 replies
@RobinBaker0512 Compare the report's sample with your incoming specification: does it describe full-panel geometry, support conditions and the film used in the actual stack?
24pointsIt used a flat sample supported underneath. The report doesn't assess the full panel geometry or say what film condition was represented
2points@RobinBaker0512 Give the tooling specialist the complete panel drawing and stack specification, requesting assessment of distributed support alongside a distinct proposal for confirming single-panel pickup.
25pointsDistributed support means more cups spread out? That's where my imagination stops, honestly
4pointsA spread of contacts is worth comparing because it can reduce unsupported panel spans. Include the edges whose positions matter during placement on the drawing used for assessment.
24pointsI'd qualify that suggestion: adding contacts doesn't establish a suitable support layout without considering local flexibility, and it doesn't answer whether one layer was acquired.
22pointsFair correction. I mean a layout assessed against your panel's flexibility, not a cup-count target. Layer confirmation remains its own requirement.
15pointsWhy can't good vacuum mean one panel? Wouldn't two make the reading different?
15pointsA cup can seal to the upper surface while another panel adheres underneath. That reading alone doesn't establish how many layers you're carrying.
21pointsI've checked our incoming records and found multiple permitted protective-film conditions. Since the quote assumes one stack condition, I'll identify that gap in the tooling request
1points@RobinBaker0512 On my panel setup, film details lived with purchasing and never reached the tooling drawing. Both teams thought 'same panel' was a complete description.
7pointsWould you put film and interleaving on the receiving spec, or just send samples? I'm trying to stop this turning into another missing attachment
17points@RobinBaker0512 Have the material supplier and process owner agree the permitted stack conditions in the specification. The sample set can then represent a defined range rather than implicitly setting it.
14pointsThe detection proposal also needs to explain an uncertain result. Failure to distinguish the supplied condition mustn't be interpreted as evidence of a single panel.
15pointsI'll ask the integrator what the confirmation method establishes and what happens when it can't decide. I won't pick a sensor from the catalogue myself
0pointsShould the support assessment cover placement as well as the panel's condition during transfer?
13points@AmaraArcher0426 The assessment should include placement and release because a satisfactory seal doesn't establish that the relevant panel edges are controlled at the receiving fixture.
19pointsThe receiving drawing identifies two placement edges. Neither appears on the supplier's contact sketch. I'll include that drawing in the support request
14points@RobinBaker0512 On my setup, adding the receiving geometry changed the discussion from 'it holds' to 'what shape arrives here'. That was a much better tooling question.
15pointsMy planning question has a clear answer: assess actual panel support and single-panel confirmation as well as sealing. I can proceed with that review while leaving transfer suitability dependent on its findings
9pointsAdd to the discussion
Welcome to Application Robot
Everyone can read the forum. Sign in or create an account to start a discussion, reply, or upload photos.
By creating an account, you agree to our Terms and Conditions and community guidelines. Read our Privacy Policy for how your information is handled.