Our FR10 bracket estimate includes correction time now, but assumes the shared correction bench is always available. That's my remaining snag: who owns the queue when a released bracket fails?
Who decides it needs correction? Put that decision before the queue in the handover, otherwise every doubtful bracket becomes somebody else's urgent job.
Then the plan needs somewhere for the bracket to wait with its identity and decision intact. Not saying build a new buffer for it. First find out what the shared bench already accepts and how production knows it has accepted the job.
And don't turn the single failed bracket in the old file into a correction rate for every order. It shows a route you need to cover. It doesn't tell you how full that route will be.
Has the bench supervisor seen the expected workload, Anika? An empty box on a process diagram is very accommodating; the person already doing other jobs may have a less cheerful answer.