Separate firm prices from allowances and excluded work. Put an owner and the missing information beside each uncertain line, or the smallest-looking total will simply be the least complete.
How do I price 163 cartons without calling every unknown included?
AlistairCampbell · 14 Jun 2026, 03:38 UTC
17 replies
One quote says training included with no scope. Another names two days but excludes staff cover. Our internal sheet treats both as zero extra cost.
6 pointsI'd ask who attends and what those days cover, Alistair. Two days with the builder operating the station may be less useful than shorter sessions where both shifts practise the approved changeover and recovery cases.
16 pointsAnd include the production time lost while people attend. Training can be included in the invoice and still cost the workshop something.
13 pointsOur first estimate also omitted spare presentation fixtures, because everyone pictured the fitted set and nobody pictured a damaged one waiting for repair while the next order arrived.
12 pointsAmara, would you buy a spare set immediately? I'd price availability and replacement lead time before making that another automatic addition to a pilot.
3 pointsNot automatically, Omar; I meant expose the cover plan and its cost, which might be a spare, repair arrangement or accepted downtime rather than another complete set on day one.
6 pointsThat distinction helps. We're estimating a production cell, but the first order is only 163. I don't want every possible contingency bought immediately or silently left with maintenance.
16 pointsFor staffing, I'd use the intended order mix rather than only the initial quantity. A single first order can show the task, but it won't represent frequent changeovers if that's what follows.
7 pointsDoes preparation begin from your real incoming cartons? Or have the proposals already unpacked them at no cost?
25 pointsOne proposal starts with arranged trays. The other includes presentation fixtures but not who fills them. Neither prices the same incoming condition as our current bench.
6 pointsThen agree that boundary before ranking. You can retain their current totals, but label what each buys instead of pretending the difference is a robot-price saving.
8 pointsLeah's preparation question should go to the people doing that work too, because our supplier's allowance looked reasonable until the operator showed how many mixed boxes arrived between changeovers.
5 pointsAmara, yes, and estimates from operators can remain estimates with their source stated. They do not need to become invented stopwatch data just because purchasing wants a comparison this week.
10 pointsRebuilt the comparison around actual incoming cartons and the same output. Internal labour allowances have named sources. Suppliers still owe preparation staffing and training scope, so neither total is final.
8 pointsHas that changed which proposal appears cheaper, Alistair? Interested whether the apparent gap survives once the excluded jobs have names.
13 pointsWhatever the answer, keep the unresolved lines on the summary page. Otherwise somebody will quote the old arm price and ask why the workshop made it expensive.
7 pointsAdd to the discussion
Welcome to Application Robot
Everyone can read the forum. Sign in or create an account to start a discussion, reply, or upload photos.
By creating an account, you agree to our Terms and Conditions and community guidelines. Read our Privacy Policy for how your information is handled.