The inspection handover has pendant screenshots showing a call to a fixture-check routine, but not that routine or its revision. I'm trying to get the missing dependencies while the integrator still remembers our housing station.
Ask the integrator to reconcile the export with the commissioned programs, including called routines, configuration, fixture assumptions and expected ordinary PLC signals. More screenshots will not make that package reproducible.
Yes, where they are supported by the installed configuration, with any relevant revisions; a spare described only as housing nest may not carry the same assumptions as the fitted one
Integrator matched the main program and supplied the called routines. One expects a different nest identifier from the stores sheet, so we're checking that before calling the handover complete.
Anika, does the integrator's package also explain the ordinary wait conditions and where maintenance can see their sources? A complete file list alone will not help the person investigating a pause.